Implementation plan · EG / UAE

EG-SPARES
Email launch

From a spare-parts enquiry to a human-issued Business Central quote. Start with one mailbox, one vendor alias, and one high-volume category.

Target launch
18 Feb 2027Assisted operation · subject to pilot and gate sign-off

13-week roadmap

18 November 2026 to 18 February 2027. Each week pairs build evidence with the input or decision Eurogulf owes.

01Confirm scope and connect the sandbox

ImplementationAgree scope, baseline and approval authority. Prove scoped mailbox read and BC lookup. Map enquiry, account lead, customer, quote and Cost Sheet.

Eurogulf deliversBy 20 Nov name the product owner, CSM, compliance lead, IT owners and primary and backup approvers. By 24 Nov provide sandbox access, BC samples and current layouts.

02Build trusted intake and extraction

ImplementationBuild header-first trust checks, safe attachment processing, line evidence and replay protection. Start masked evaluation and structure pricing rules.

Eurogulf deliversProvide at least 50 labelled masked cases, current volumes, turnaround, win and error rates, minimum data, scope rules, domain registry, blocklist and sample rates.

03Connect part review and RFQ drafting

ImplementationBuild BC match, completeness, scope checks and Account Lead queue. Generate acknowledgement and RFQ drafts from the sandbox enquiry and scan for leaks.

Eurogulf deliversSupply approved parts sources, vendor mapping and disclosure rules, customer restrictions, templates, calendar and escalation matrix. Name policy owners.

04Demonstrate on 11 December

ImplementationShow normal and blocked cases through vendor quote ingestion. Show a traced sandbox Cost Sheet if the pilot pricing rules are usable.

Eurogulf deliversCSM, Procurement and IT review the demo. Finance agrees pricing tolerance and sign-off. Compliance confirms tool and integration path.

05Complete pricing and quote exceptions

ImplementationHandle quote revisions, urgent and combined quotes, maximum wait and quote expiry. Connect screening and prove failures block sends.

Eurogulf deliversProvide the pricing register and historical lines for back-testing, screening access and policy. Resolve provider region, DPA, retention and live-data terms by 22 Dec.

06Prove confidentiality and recovery

ImplementationRun historical and pricing tests. Prove the BC customer layout and Exchange DLP. Rehearse outages, retries, restore and HALT.

Eurogulf deliversApprove the evaluation set and confirm January reviewer and holiday coverage.

07Start read-only live shadow

ImplementationFinish launch-scope fixes. Start shadow by 5 Jan. Compare outputs to staff work without live writes or external sends.

Eurogulf deliversAuthorize the shadow feed after data terms are approved. Confirm the daily review rota and assign owners and dates for all outstanding gates.

08Measure shadow week one

ImplementationMeasure extraction, parts, routing, pricing and safe failures. Fix issues and replay affected evidence.

Eurogulf deliversAccount Leads, Procurement and CSM label outcomes daily. Finance resolves pricing discrepancies.

09Measure shadow week two

ImplementationSeek exit on two consecutive weeks meeting agreed thresholds. Extend shadow if needed and reassess evidence after material changes.

Eurogulf deliversCSM reviews shadow results. Policy owners publish approved versions. IT and Compliance sign their controls.

10Run user acceptance testing

ImplementationAfter shadow exit, test mixed and urgent lines, ambiguous parts, corrections, disclosure, pricing judgment, approval timeouts and recovery.

Eurogulf deliversNamed testers run cases and sign. Process owners, Procurement, Compliance and IT resolve open items.

11Decide whether the pilot can start

ImplementationClose blocking defects, freeze pilot configuration, train approvers and rehearse rollback and manual processing. Hold go/no-go on 2 Feb.

Eurogulf deliversSign all 11 production gates. Confirm categories, vendor allowlist, approver coverage and HALT authority.

12Run controlled pilot week one

ImplementationReview approved EG traffic, sends, Cost Sheets and exceptions daily. Compare correctness, response time, turnaround and incidents with baseline.

Eurogulf deliversStaff the approval queue. CSM leads daily triage and decides whether to continue, pause or limit traffic.

13Finish the pilot and hand over

ImplementationComplete pilot week two and hand over the runbook, dashboard, incident procedures and launch evidence.

Eurogulf deliversUse-case owner and Chief AI Officer sign go-live with Governance Board approval at the applicable gate.

↗Open the approved EG scope

ImplementationLaunch assisted operation if pilot criteria are met, production gates are closed and operational owners are ready.

Eurogulf deliversConfirm production coverage, hypercare and post-launch measurement ownership.

Schedule dependency. A third shadow week uses most of the contingency. Four weeks of shadow, a critical defect, or an open gate on 2 February moves the live pilot and launch dates.

11 December milestone

Show one EG category from test email through the sandbox quote hand-off. A traceable Cost Sheet depends on usable pricing rules.

Open the milestone and task plan →

Enquiry to quote

Follow the email enquiry, vendor RFQ, deterministic pricing, and human quote hand-off, including the exception paths.

Open the workflow diagrams →

Launch gates

Close and sign every production gate before approved live pilot traffic. Evidence determines whether the plan advances.

  1. Sandbox proof
  2. Read-only shadow
  3. Signed UAT
  4. 11 gates closed
  5. Two-week pilot
  6. Assisted launch
  • Sanctions and export screeningCompliance · Named owner, screening policy and tool, with fail-closed tests.
  • Deterministic pricingCSM, Finance and Management · Structured pricing register, historical back-test and approval.
  • Model-provider data termsIT and Legal · Region, DPA and retention approved before live shadow.
  • BC quote layout and DLPIT and BC team · Evidence that restricted part identifiers cannot leave via the new quote flow.
  • Category minimum dataCSM · Required fields and validation for launch categories.
  • Approved part sourcesSpares technical lead · Allowed sources and evidence independence groups.
  • RFQ templatesProcurement and CSM · Category templates with field and leak checks.
  • Business calendarNamed calendar owner · Holidays, working hours and follow-up timing.
  • Policy ownershipProduct owner · Named owner for each policy and approved published versions.
  • Operational baselineCSM and Finance · Signed time-to-quote, win rate and error measurements.
  • Domain registrySales Ops and IT Security · Named owner, seeded customer and vendor domains, and approval workflow.

Team and owners

Plan for four to five implementation people at approximately 3.75–4.5 full-time equivalents, plus security support for testing and release.

Implementation

Technical lead · 0.5–0.75 FTEDesign, delivery, dependency decisions and release evidence.
Workflow and AI · 1 FTEIntake, extraction, routing, drafts, review queue and evaluation.
BC and M365 · 1 FTEGraph access, BC objects and contracts, Cost Sheet, quote layout and DLP.
Backend and pricing · 0.75–1 FTEPricing service, rule tests, trace and outage handling.
QA and release · 0.5–0.75 FTETest evidence, resilience, release rehearsal and UAT support.

Eurogulf

Product owner and CSMReserve two to three days a week in readiness and daily availability in shadow and pilot. Own scope, pricing policy and launch triage.
Account Lead and backupResolve exceptions with a named parts specialist. Cover the approval queue during operating hours.
Procurement, Finance and ComplianceOwn vendor rules, financial sign-off, screening policy and escalations.
IT, BC, Legal and UAT testersProvide scoped access, provider terms, publishing controls, and signed test results. Confirm who can halt production.

Later releases

  • Rollout. AK and MEMA, more categories and vendors, WhatsApp, the mobile app, and other divisions.
  • Higher autonomy. Promote approved acknowledgement, RFQ, follow-up, verified-answer and master-data actions class by class. Keep final quoting, pricing judgment and compliance exceptions human-owned.
  • Deeper functionality. Broader catalogue search, vendor portals, advanced data enrichment, learning proposals and richer reporting. The February release includes the review queue, HALT and Decision Log.
  • Other programme work. OKRs, lead generation and department process redesign have their own scope and gates.

Planning assumptions. Gate closure and build progress are unverified. Add a second pilot category only when its rules and testing are ready by shadow start. Have Eurogulf approve the scope and any Phase 1 deferrals.